F.J Construction (PTY) And Another v United General Holdings (525 of 2022) [2025] SZHC 394 (11 June 2025)

EswatiniLII

Automated Summary

Key Facts

The case involves United General Holdings (Plaintiff/1st Applicant) seeking payment of E1,678,117.69 from F.J Construction (PTY) (1st Defendant/Respondent) and Joseph Nkambule (2nd Defendant/2nd Applicant) after the plaintiff fulfilled its obligation under a JBCC Guarantee for Construction. The employer (ESwatini Building Society) terminated the construction contract with F.J Construction due to default, triggering the guarantee. The court granted summary judgment, ruling the plaintiff was not bound by the JBCC Principal Agreement's dispute resolution mechanism and had a clear contractual obligation to pay upon termination notice. The defendants' arguments regarding arbitration jurisdiction and employer's breach were dismissed, as the plaintiff's liability stemmed from the separate guarantee agreement.

Transaction Type

JBCC Principal Building Agreement between Swaziland Building Society and F.J Construction (PTY)

Issues

  • The court addressed the argument that the Plaintiff, as a third party to the JBCC Principal Agreement, should be bound by its dispute resolution mechanism (arbitration). The court held that the Plaintiff is not a party to the agreement and thus cannot be bound by its terms, rejecting this preliminary objection.
  • The second issue concerned the validity of the employer's termination of the construction agreement. The court determined that the Plaintiff's contractual obligation to pay upon demand was not contingent on the termination's legality, as that was the contractor's responsibility. The court found no triable issue here.

Holdings

  • The court granted summary judgment in favor of the Plaintiff, ordering payment of E 1,678,117.69, interest at 9% per annum from the date of payment, and costs of suit.
  • The Defendant's argument that delays were caused by employer-nominated subcontractors did not constitute a valid defense to the Plaintiff's claim, absent allegations of fraud or collusion.
  • The Plaintiff's obligation to pay the guarantee was triggered by valid termination of the contract by the employer due to the 1st Defendant's default, and the Defendant failed to challenge the termination or payment demand.
  • The Plaintiff was not a party to the JBCC Principal Agreement and thus not bound by its dispute resolution mechanism, invalidating the Defendant's preliminary objection to the court's jurisdiction.

Remedies

  • Interest was granted at a rate of 9% per annum as part of the summary judgment.
  • The court ordered the payment of E1,678,117.69 as part of the summary judgment.
  • The court awarded the costs of the suit to the plaintiff as part of the summary judgment.

Monetary Damages

1678117.69

Legal Principles

  • The doctrine of privity of contract, which states that only the parties directly involved in a contract can enforce its terms or be held liable under it. The court emphasized that the Plaintiff, as a third party not a signatory to the JBCC Principal Agreement, cannot be bound by its dispute resolution mechanisms.
  • The principle that contracts must be enforced according to their terms. The court noted this as a foundational contractual principle, affirming the Plaintiff's obligation to honor the guarantee once validly called upon.

Precedent Name

  • Beauty Nonzima Nxoko – Banko N.O v Xolani Eshwell Mpolongwane
  • Mater Dolorosa High School V RJM Stationary (pty) LTD

Key Disputed Contract Clauses

  • Clause 8.0 required the Plaintiff to pay within 7 calendar days of demand. The court confirmed compliance with this clause, as the Plaintiff paid within the stipulated period.
  • Clause 5.0 obligated the Plaintiff to pay the guaranteed sum upon termination notice. The Defendants did not challenge this clause's validity but contested the termination's lawfulness.
  • The Defendants argued the court lacked jurisdiction, asserting the JBCC Principal Agreement required arbitration. The court held the Plaintiff, not being a party to the agreement, was not bound by its arbitration clause.
  • The employer terminated the contract under this clause, which the Defendants contested as unlawful. The court determined the termination clause was validly invoked by the employer.

Cited Statute

  • Rule 32 of the High Court Rules of Eswatini
  • Rule 32 (4) (a) of the High Court Rules of Eswatini

Judge Name

Z. Magagula

Passage Text

  • The doctrine of privity of contract prevents parties who are not privy to the contract to be bound by the contract.
  • It would be more accurate to say that a court will not merely 'be slow' to close the door to a defendant, but will refuse to do so if a reasonable possibility exists that an injustice may be done if judgement is summarily granted.
  • The Plaintiff is not a party to the Principal agreement and it boggles the mind how it may be expected to be bound thereby.

Damages / Relief Type

  • Interest at 9% per annum from the date of payment
  • Costs of suit awarded to the plaintiff
  • Payment of E1,678,117.69 as compensatory damages