Zimbabwe Power Company (appellant) and Intratrek Zimbabwe (respondent) entered into a Public Procurement Engineering, Procurement and Construction Contract on 23 October 2015 for a 100MV solar power station in Gwanda. The contract's commencement was subject to suspensive conditions, including securing funding and completing feasibility studies, which were to be fulfilled within 24 months. An addendum in September 2017 extended timelines for pre-commencement works, but the appellant failed to pay for these works, leading to disputes. The appellant terminated the contract in late 2017, citing the respondent's failure to meet conditions, while the respondent claimed the appellant intentionally frustrated financing agreements. The court a quo found the contract valid and binding, ruled that the appellant's actions caused the failure to meet conditions, and ordered specific performance. The appeal against this judgment was dismissed by the Supreme Court.
Transaction Type
Engineering, Procurement and Construction (EPC) Contract for Solar Power Station
Issues
- The court reviewed the validity of the counterclaim for pre-commencement works, noting the respondent's evidence that the works were completed and the appellant's failure to prove the claim through its sole witness.
- The court assessed whether the appellant's actions, including signing an addendum and attempting to extend the conditions precedent period, constituted a waiver under the contract terms, despite the respondent not formally pleading this.
- The court examined whether its earlier decision in SC 39/21, which dismissed an application on procedural grounds, contradicted the court a quo's findings that the contract remained valid despite the respondent's admission of non-fulfilment of conditions precedent.
- The court evaluated if the doctrine of fictional fulfilment applied, requiring proof that the appellant intentionally frustrated the financing conditions, thereby deeming them fulfilled to prevent the appellant benefiting from its wrongdoing.
- The court determined if the respondent's evidence on financing issues and allegations of malicious conduct, though not in the original declaration, was properly considered as part of the pleaded case under applicable legal principles.
- The court considered the appropriateness of granting specific performance despite the appellant's claims of impossibility and hardship, relying on evidence that the respondent could secure funding and the contract remained viable.
Holdings
- The counterclaim for USD 3,310,736.30 was dismissed with costs, as the court found no evidence to support the appellant's refund claim.
- Specific performance of the contract was ordered, dismissing the appellant's argument that it would cause undue hardship or be unviable.
- The court found the EPC contract valid and binding between the parties, rejecting the appellant's res judicata defence and affirming the court a quo's determination.
- The court ruled that the conditions precedent were fictionally fulfilled due to the appellant's intentional frustration of financial arrangements, precluding termination.
Remedies
- The court dismissed the appellant's counterclaim seeking a refund of USD 3,310,736.30 for pre-commencement works. The dismissal was with costs, as the evidence showed the respondent had performed substantial work warranting payment. The counterclaim lacked sufficient substantiation given the uncontroverted testimony about completed works.
- The Supreme Court awarded the costs of the appeal to the respondent. This included legal expenses from both the appeal (SC 127/23) and the underlying court a quo proceedings (SC 38/23). The costs award followed the dismissal of the appeal and affirmed the respondent's position in the litigation.
- The Supreme Court dismissed the appellant's appeal against the court a quo's decision. The appeal was found to lack merit, particularly regarding claims of res judicata, procedural errors, and the viability of the contract. The court upheld the validity of the EPC contract and the order for specific performance.
- The court ordered specific performance of the Engineering, Procurement and Construction (EPC) contract for the 100MW Gwanda Solar Project. This remedy required the parties to fulfill their contractual obligations despite the appellant's claims about financial viability and termination. The court found the contract remained valid and binding after waiving conditions precedent and invoking fictional fulfilment due to the appellant's intentional frustration of financial closure.
Contract Value
172848597.60
Legal Principles
- The court a quo rejected the appellant's res judicata defense, determining that this Court's decision in SC 39/21 was limited to procedural grounds and did not preclude re-litigation of the substantive issues. The court emphasized that no merits were decided in the prior appeal.
- The court applied the doctrine of estoppel, finding that the appellant's intentional frustration of financial agreements estopped it from terminating the contract. The fictional fulfillment of the financing condition was deemed appropriate, aligning with established case law on estoppel and intentional obstruction.
Precedent Name
- Grandwell Holdings (Pvt) Ltd v Zimbabwe Mining Development Corporation & 3 Ors
- Scott & Anor v Poupard & Anor
- Standard Chartered Bank Zimbabwe Ltd v Matsika
- Shah v Kingdom Merchant Bank
- Hama v National Railways of Zimbabwe
- Benson v SA Mutual Life Assurance Society
- His Holiness Acharya Swami Dasji
- Mia v Verimark Holdings Pty Ltd
- Transnet Ltd v Goodman Brothers Pty Ltd
- Minister of Public Construction and National Housing v Zescon (Pvt) Ltd
Key Disputed Contract Clauses
- Clause 6 required written amendments for contract changes. The court held the appellant's unilateral extension of the satisfaction period violated this clause, as no mutual written amendment occurred.
- The court analyzed the conditions required for contract commencement under Clause 5, including financing and feasibility studies. It found the addendum extended the satisfaction period, and the appellant's intentional frustration of financing led to fictional fulfillment of these conditions.
- The addendum modified the original contract's conditions, permitting pre-commencement works and extending the satisfaction period. The court ruled it valid and integral to the contract, invalidating the appellant's unilateral termination claim.
Cited Statute
Supreme Court Rules
Judge Name
- Chiweshe
- Makoni
- Musakwa
Passage Text
- The court a quo found that the procurement contract for the 100 MW Gwanda Solar Project (ZPC 304/2015) between the plaintiff and the defendant as amended is valid and binding between them.
- The court a quo found that the appellant purposefully prevented or frustrated the fulfilment of the condition precedent pertaining to the signing of the financing agreements.
- The court a quo held that the counter claim could only become relevant if it had held that the contract did not commence as a result of the respondent's failure to fulfil the conditions precedent.
Damages / Relief Type
- Order for specific performance of the EPC contract granted
- Appellant's counterclaim for USD 3,310,736.30 dismissed with costs